Commissioning of the ENIPOWER Ravenna cooling system (2003).
2003
-
Tower conversion from Wet to Wet/dry ENEL Fusina power plant consisting of 12 cells.
-
Assembly of the ANSALDO cooling tower in Rosignano (Li) with 6 cells.
-
Installation of the Termoli Ecoenergia cooling tower, consisting of 12 cells.
-
Revamping of the EnelGreenPower Natural Draft Tower in Larderello and the S. Barbara Power Plant (AR) with the installation of antifreeze piping around the circumference of the tower.
-
Maintenance at CERN in Geneva
-
SOL cooling tower assembly in Belgium .
2006-2007
-
Marcinel Enel Belgium combined cycle turbo gas power plant, assembly of 8 complete cells with electrical and instrumentation system.
-
Pego Simens combined cycle turbo gas power plant with 16 cell assembly.
-
Blenod EDF France combined gas turbo power plant, assembly of 10 FRP cells complete with electrical and instrumentation system.
2009-2010
-
Assembly of Novara STC Wet/dry cooling tower composed of 4 cells (2005).
-
Assembly of the Granarolo ERA Wet/dry cooling tower, consisting of 3 cells and maintenance (2005-2006-2007-2008).
-
SARAS Sarroch Plant Maintenance (2005-2006-2007).
2005
-
Total refinery in Le Havre ( France ), assembly of a wooden tower composed of 4 cells
-
ELECTRABEL power plant in Charleroi : revamping the tower and natural draft.
-
Revamping of a concrete tower composed of 4 cells La Rochette power plant in Ferney, France , assembly of a tower composed of two FRP cells.
2008
-
Engineer Germany at SWN Germany Neumuster three FRP cells.
-
Fata Pec Iren Turin combined gas turbo power plant, assembly of 12 wet/dry FRP cells.
-
Assembly of 22 FRP cells at Qatalum Doha Qatar turbo gas power plant.
-
Assembly of 3 wooden cells at the Okawe biomass power plant in Eberswalde, Germany .
-
Polimeri Europa (SR)/Versali. Demolition of the SCAM package tower and the tower feedwater supply and return system. Prefabrication and installation of new piping and installation of new cooling towers with related electrical and instrumentation systems.
2011-2012-2013
2014-2015
-
Air condenser Chaufferie Biofely, Epinal France , number of cells 2. Installation up to commissioning and testing, including the steel supporting structure, heat exchangers, mechanical groups, exhaust turbine, manifold and alignment, steam distributor, instruments.
-
Sitcome air-cooled condenser, Benesse Maremne, France , 2 cells, dimensions 15x30. Installation through commissioning and testing, including the steel supporting structure, heat exchangers, mechanical units, exhaust turbine, manifold and alignment, steam distributor, and instruments.
-
Air condenser Centre Valarisation Energetique, Laubrevier France , number of cells 4. Installation up to commissioning and testing, including the steel load-bearing structure, heat exchangers, mechanical groups, exhaust turbine, manifold and alignment, steam distributor, instruments.